page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10 page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28
page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49
page 50
page 51
page 52
page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67
page 68
page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101
page 102
page 103
page 104
page 105
page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124
page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138
page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
< prev - next > Energy Hydro power civil_works_guidelines_for_micro_hydro (Printable PDF)
8 CIVIL WORKS GUIDELINES FOR MICRO-HYDROPOWER IN NEPAL
site to site and project to project. Project layout arrangements
shown in Figure 2.0 are combinations of weir and intake,
intake canal, spillway, gravel trap, approach canal, settling
basin, headrace canal/pipe, forebay, penstock and the
powerhouse. The five layout arrangements shown in the
figure are briefly discussed herein.
Layout 1
Layout 1 is a standard type of micro-hydro project layout
arrangement with most components included. This type of
project layout arrangement is used in case of higher design
flows (300 l/s or above) from a relatively large river. Due to
the large flow that can enter into the water conveyance system
its management as well as sediment exclusion has higher
importance. Thus, all standard structures of a micro–hydro
project are required.
Layout 2
The difference in this layout compared to Layout 1 is that
the headrace canal or pipe is replaced with a longer penstock
pipe. Generally headrace canal or headrace pipe is preferred
along gentle ground profile due to its low cost compared to
loss in head (and therefore lower installed capacity). However,
sometimes if a detailed financial analysis justifies a long
penstock length with the initial alignment along gentler
slopes, then the arrangement can be similar to Layout 2 in
the figure above. One technical consideration required with
longer penstock pipe is surge pressure due to water hammer
which can be high and need to be addressed adequately.
Layout 3
If sufficient flow is available and river sediments is not a
problem, such as in case of streams with very small catchment
area or those originating from spring sources, then arrangement
similar to Layout 3 maybe suitable. This arrangement requires
only flow diversion and submergence condition at weir and
intake location for the penstock. Similar to Layout 2, surge
pressure may become higher in this arrangement.
Layout 4
In this arrangement, a separate settling basin is not
incorporated; rather, it is combined with the forebay at the
end of the headrace. This type of layout is possible in the
case of small stream with low flow diversion and nominal
sediment load (in the river) during flood. Furthermore, if the
river flow is extremely low and provision for storage can be
made at the forebay such as by constructing a larger tank,
then the water can be stored during the off period (e.g., night
time) for use during the peak hours (e.g., mornings and
evenings). In such a case the forbay tank with storage will
also take the function of a settling basin if flushing
mechanism is also incorporated.
Layout 5
Though very rare, sometimes it may be feasible to construct a
small storage pond on the river itself, especially if the source is a
small (and clean) stream or a spring (instead of the forebay in
Layout 4). River water would be stored in this pond during off
hours for use during the peak hours. This arrangement will avoid
the need for longer headrace canal/pipe and the forebay, i.e., the
penstock starts from the pond which also acts as a forebay.
2.4 Geotechnical considerations
2.4.1 GEOLOGY
The geology of the site is critical to the design, costs and
future performance of the civil works of micro-hydro schemes.
Geological maps of certain areas of Nepal are available at the
Department of Mining and Geology or Tribhuvan University’s
geological library. It is worth checking whether such a map is
available for the area of interest since this will indicate the
general geological condition of the site.
Geological characteristics of a site can be grouped in the
following ways:
Major weakness zones - Large areas of geological instability
in the areas where the civil structures are to be located.
Slope stability - The degree of stability of the hillsides of
the site.
Soil and rock types - Foundation conditions and liability to
seepage undermining and subsidence around structures
planned for the site.
2.4.2 MAJOR WEAKNESS ZONES
The main tectonic zones of the Himalayas generally correspond
to the physiographic divisions of the country and run in
northeast-southwest direction. Major weakness zones such
as thrusts or faults separate these zones from each other. In
addition there are many other “minor” weakness zones which
Figure 2.3 Threat to structures from below due to landslip.
Figure 2.4 Threat to structures due to falling debris from above